PROJECT UPDATES ARCHIVE
DATE: April 23rd, 2026
SCHEDULE UPDATE: MILLING
SCHEDULE UPDATE: Due to scheduling adjustments, Emery Sapp & Sons will begin preliminary roadway milling operations along Route 2 on Tuesday, April 28, 2026.
Milling activities will include curb milling along S. Independence Street to the intersections of W. South Street and Route 2. Crews will also perform depth transition cuts at all side streets, entrances, and concrete/asphalt driveways. These transitions are necessary to provide a smooth and consistent connection between existing pavement and the new roadway surface.
Motorists are advised to use caution, remain alert for workers, and follow all posted flagger instructions while traveling through the work zone.
Work is anticipated to take approximately 2–3 days and will begin after 8:00 a.m. each day to minimize impacts to morning traffic.
The paving schedule remains on track to begin May 4, weather permitting.
Emery Sapp & Sons appreciates the public’s cooperation and is committed to maintaining a safe and efficient work zone for all.
DATE: April 20th, 2026
Road Closure Notice(s)
Emery Sapp & Sons will have employee-owners distributing Road Closure Notices throughout Harrisonville neighborhoods on April 21, 2026. These notices will provide detailed information regarding upcoming access closures, traffic guidance, and instructions for navigating the work zone. A QR code linking directly to this project website will also be included for easy access to updates.
Construction activities remain on schedule, with paving operations in Harrisonville anticipated to begin on May 4, 2026, at 8am.
DATE: April 14th, 2026
Locates & Post Mount Sign Install
Subcontractor Streetwise will have locates done the week of April 13th to mark out post mounted traffic control signs.
Streetwise will begin installing the post mounted traffic control signs along Route 2 from Harrisonville to La Tour the following week of April 20th in advance of construction starting.
DATE: April 14th, 2026
Asphalt Plant Update
Emery Sapp & Sons is in the process of erecting their portable asphalt plant at their Garden City plant site. Construction is estimated to start on Monday May 4th. If you have any large-scale asphalt projects you would like to buy mix for, or if you are interested in having ESS do the work for you, reach out to Darren Woods at (573) 228-7079 darren.woods@emerysapp.com
DATE: April 14, 2026
Project Updates Website
This website has been created to keep the public informed on Modot project JKU0049. Our goal is to provide clear, timely, and accessible information so residents, businesses, and travelers can plan ahead with confidence.
Here, you can view project plans, specifications, traffic control maps, and the latest construction schedules. We encourage you to subscribe for updates to receive important notifications and progress reports directly.
Your awareness and cooperation are greatly appreciated as we work to complete this project as efficiently and safely as possible.
For the latest project insights and schedule changes, subscribe to our project updates emails group.